CASE STUDY

Granny Smith Solar Farm

Harnessing our expertise in the emerging renewables construction sector, RE:GROUP was commissioned to self-manage the installation and mechanical works. We successfully delivered the project within five months, while maintaining high safety and production standards.

/   Pre-drilling of piling holes and pile installation
/   Installation of comprehensive solar tracker, drive motors and panels
/   Construction of ring roads and in roads to the transformer pads
/   Construction of transformer pads and laydown, carpark, and office areas
/   Fencing installation
/   Trenching and earthing grids 

RE:GROUP Wet and Dry Hire in The Pilbara Civil and mining contracting branding element

Location

Laverton, WA

Client

Aggreko

Completion

Dec 2019